Question 1

When creating a project from demand, what related records are moved and copied upon Project Creation?

Options:

A.

Resource Plan and Cost Plan.

B.

Resource Plan and Change Requests.

C.

Idea and Demand.

D.

Cost Plan and Assessment.

Question 2

When can a user choose from multiple rate types for their work, while logging a time card?

Options:

A.

Only if the capability is enabled in the Time Sheet Policies

B.

Only if this capability is enabled in the Project Record

C.

Only one (1) rate type can apply

D.

Only if the capability is enabled in the Project Preferences

Question 3

The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?

Options:

A.

Journal.

B.

Reference.

C.

Conditions.

D.

List.

Question 4

Which related lists should primarily be used to capture financial data in a project?

Choose 2 answers

Options:

A.

Programs

B.

Cost Plans

C.

Risks

D.

Monetary Benefit Plans

Question 5

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Options:

A.

Accrual

B.

Commitment

C.

Baseline

D.

Forecast

Question 6

Which of the following can be used to calculate planned cost when creating a resource plan?

Choose 2 answers

Options:

A.

Demand rate

B.

Rate card

C.

Default rate

D.

Project rate

Question 7

In which table can you find cost information for a specific fiscal period?

Options:

A.

cost_plan_breakdown

B.

pm_project

C.

cost_plan

D.

expense_line

Question 8

What are the default project template configuration records available in the Template Config module?

Choose 3 answers

Options:

A.

Project task

B.

Project subtask

C.

Project

D.

Task

E.

Project template

Question 9

Which role can configure the parameters of the demand workbench that is provided with the base system?

Options:

A.

All roles.

B.

business_stakeholder.

C.

it_project_manager.

D.

it_pps_admin.

Question 10

Which statement defines the Project Workspace?

Options:

A.

A central location to view of all projects in a portfolio to prioritize work

B.

A central location for creating and managing projects

C.

A central location transform the navigation of lists and forms into an interactive graphical experience

D.

A central location for viewing and assessing business demands

Question 11

What is the formula for Committed Utilization?

Options:

A.

Assigned Hours/Capacity

B.

(Allocated Hours + Confirmed Hours)/Capacity

C.

Confirmed Hours/Capacity

D.

Allocated Hours/Capacity

Question 12

Which demand category would a demand manager select, if they need to create an enhancement?

Options:

A.

Defect

B.

Change

C.

Operational

D.

Strategic

Question 13

The project property to update actual effort from time card is controlled at what level?

Options:

A.

Application Level (Global).

B.

Portfolio Level.

C.

Program Level.

D.

Project Level.

Question 14

If a lens has four entities, which entity within the lens structure would not have a parent reference?

Options:

A.

Top-level entity

B.

Second-level entity

C.

Third-level entity

D.

Bottom entity

Question 15

Can an it_project_manager convert a task to a milestone?

Options:

A.

No, this can only be done by a system admin.

B.

Yes, if the task is assigned to the project manager.

C.

Yes, by right-clicking on the task in the Planning Console.

D.

No, the PPS admin role is also required.

Question 16

Which plugin activates the Ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation?

Options:

A.

Test Management 2.0

B.

Agile Development 2.0

C.

Ideation with PPM

D.

Resource Management

Question 17

Idea [im_idea_core] is directly extended from which table?

Options:

A.

It is not extended from any table

B.

Task

C.

Idea Modules

D.

Project

Question 18

Demand assessments are triggered as soon as the demand enters what state?

Options:

A.

Approved.

B.

Screening.

C.

Qualified.

D.

Submitted.