Question 1

Which statement describes a cadence-based PI Planning event?

Options:

A.

As many team members as possible should attend remotely to reduce travel costs

B.

It is very important and should be postponed until all participants can attend

C.

It is not a required event but tasks move forward at higher velocity when the meeting occurs

D.

It is an all-hands, two-day event with the goal to create alignment

Question 2

Which type of decision should remain centralized even in a decentralized decision-making environment?

Options:

A.

Decisions that come with a high cost of delay

B.

Decisions that deliver large and broad economic benefit

C.

Decisions that require local information

D.

Decisions that are made frequently

Question 3

Which of the following SAFe Agile Team types relies on a continually-refined Team Backlog as the primary input to drive value delivery?

Options:

A.

SAFe Team Kanban

B.

SAFe Lean Team

C.

SAFe Epic Team

D.

SAFe Co-located Team

Question 4

What best describes the process of the confidence vote?

Options:

A.

Business Owners vote

B.

The teams and the ARTs vote

C.

The managers vote

D.

Each person votes

Question 5

James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?

Options:

A.

Support adding an Innovation and Planning Iteration directly after the current Iteration

B.

Agree to add a person from the System Team to complete the work

C.

Ensure the Iteration backlog is accurately prioritized

D.

Support splitting a Story into a coding story and a testing story, and then moving the testing story into the next Iteration

Question 6

What is the purpose of the Iteration review?

Options:

A.

To serve as a forecasting meeting where the work is estimated for the Program Increments

B.

To show the backlog items and work on possible Solutions for the backlog items

C.

To measure the team's progress by showing working Stories to the stakeholders and getting ^ feedback from them

D.

To identify where there is too much work in the system and where the teams are being ^ overloaded

Question 7

Which statement is true about work in process (WIP) limits?

Options:

A.

Higher WIP limits provide richer feedback

B.

Higher WIP limits result in lower utilization

C.

Lower WIP limits improve flow

D.

Lower WIP limits result in fewer Stories being completed

Question 8

What are two reasons Agile development is more beneficial than waterfall development? (Choose two.)

Options:

A.

It requires phase-gate approvals to ensure that everyone is moving together

B.

It increases productivity and employee engagement

C.

It allows businesses to deliver value to the market more quickly

D.

It relies on external provider dependencies

E.

It allows management to track project progress based on steering committees and metrics

Question 9

Which statement describes one element of the CALMR approach to DevOps?

Options:

A.

Build cross-functional Agile Release Trains around the flow of value to the Customer

B.

Keep everything under version control

C.

Establish a work environment of shared responsibility

D.

Decentralize decision making

Question 10

During System Demo, Team B states that the most recent release failed because of poor version control. They share their plan for preventing similar mistakes from happening in the future. Which of the following SAFe Core Values is Team B demonstrating?

Options:

A.

Organize around value

B.

Siloed Thinking

C.

Transparency

D.

Visualizing work

Question 11

What can be used to script the change to SAFe?

Options:

A.

The Lean-Agile Center of Excellence (LACE) charter

B.

The portfolio canvas

C.

The steps in the Business Agility

D.

The SAFe Implementation Roadmap

Question 12

Which statement applies to uncommitted objectives?

Options:

A.

They are included in the commitment

B.

They are items the team has high confidence in

C.

They are counted when calculating load

D.

They are extra things teams can do if they have time

Question 13

Team B has elected to stop holding retrospective events so they can spend more time completing Stories. Which of the following Agile Team responsibilities is Team B over-prioritizing?

Options:

A.

Applying systems thinking

B.

Deliver value

C.

Plan the work

D.

Connect with the customer

Question 14

Which statement is true about batch size?

Options:

A.

Large batch sizes ensure time for built-in quality

B.

The handoff batch should be made as large as possible

C.

When Stories are broken into tasks, it means there are small batch sizes

D.

Large batch sizes increase variability

Question 15

Which two views does the Iteration review provide into the program? (Choose two.)

Options:

A.

How the team is responding to the stakeholders

B.

How the team is doing on the Program Increment

C.

How the team is increasing empowerment

D.

How the team is demonstrating transparency of decision-making

E.

How the team did on the Iteration

Question 16

Deploy, verify, monitor, & respond are all activities of what?

Options:

A.

Continuous Integration

B.

Continuous Exploration

C.

Continuous Deployment

D.

Release on Demand

Question 17

Which is an aspect of systems thinking?

Options:

A.

Mastery drives intrinsic motivation

B.

Optimizing a component does not optimize the system

C.

The length of the queue impacts the wait time

D.

Cadence makes routine everything that can be routine

Question 18

Which of the following design-thinking techniques helps break down Features while considering the end-to-end user flow?

Options:

A.

Story Mapping

B.

Personas

C.

Gemba walks

D.

Market research

Question 19

Which of the following tools can be used to develop a deeper understanding of what customers are seeing, thinking, and feeling while interacting with the Solution?

Options:

A.

Value stream map

B.

Story map

C.

Empathy map

D.

Vision map

Question 20

What is one quality practice for software development?

Options:

A.

Rapid prototyping

B.

Refactoring

C.

Continuous exploration

D.

Modeling and simulation

Question 21

Which practices are demonstrated during the Inspect and Adapt event?

Options:

A.

New start, job sequence, funnel, and enable

B.

Reflect, problem solve, and identify improvement actions

C.

Move forward, analyze future Stories, integrate, and iterate

D.

Forward focus, develop, cross-domain plan, and expedite execution

Question 22

What is the purpose of Customer Centricity?

Options:

A.

To design custom-built Customer Solutions

B.

To interpret market rhythms

C.

To build small, partial systems just in time

D.

To understand the Customer's needs

Question 23

What is one of the Product Owner's responsibilities?

Options:

A.

To manage and prioritize the Team Backlog

B.

To foster normalized estimating within the team

C.

To foster adoption of Agile technical practices

D.

To facilitate team meetings and drive Agile behavior

Question 24

Which of the stakeholders primarily develops the definition of done for the team increment?

Options:

A.

Release Train Engineer

B.

Business Owners

C.

Agile Teams

D.

Solution Architect

Question 25

What are the three parts of Inspect and Adapt?

Options:

A.

The PI System Demo, confidence vote, and ROAMing risks

B.

Backlog refinement, qualitative and quantitative measurement, and ROAMing risks

C.

Backlog refinement, confidence vote, and Problem-Solving workshop

D.

The PI System Demo, qualitative and quantitative measurement, and Problem-solving workshop

Question 26

Which of the following roles is responsible for prioritizing the Agile Team Backlog?

Options:

A.

Release Train Engineer

B.

Scrum Master/ Team Coach

C.

Release Manager

D.

Product Owner

Question 27

What is considered an anti-pattern when assigning business values to team PI Objectives?

Options:

A.

Business values are assigned to uncommitted objectives.

B.

High business value is assigned to important Enabler work.

C.

Business Owners assign the business value for all teams on the ART.

D.

All PI Objectives are given a business value of 10.

Question 28

According to SAFe Lean-Agile Principle #10, what should the Enterprise do when markets and customers demand change?

Options:

A.

Apply development cadence & synchronization to operate effectively & manage uncertainty

B.

Create a new Portfolio to manage the change

C.

Create a reliable decision-making framework to empower employees

D.

Reorganize the network to address emerging opportunities

Question 29

Who is responsible for managing the Portfolio Kanban?

Options:

A.

Product Management

B.

Release Train Engineer

C.

Solution Management

D.

Lean Portfolio Management

Question 30

What is one key purpose of DevOps?

Options:

A.

DevOps focuses on a set of practices applied to large systems

B.

DevOps joins development & operations to enable continuous delivery

C.

DevOps enables continuous release by building a scalable Continuous Delivery Pipeline

D.

DevOps focuses on automating the delivery pipeline to reduce transaction cost

Question 31

What is the role of the Release Train Engineer?

Options:

A.

To ensure the technical integrity of all development in the Agile Release Train

B.

To coach teams to improve their results

C.

To serve as the content authority at the Program Level

D.

To serve as the Scrum Master for the Agile Release Train

Question 32

Which statement is true about the purpose of a work in process constraint?

Options:

A.

It encourages collaboration and enables flow

B.

It captures where all new "big" ideas come from

C.

It helps analyze, approve, and track Portfolio Epics and Enablers

D.

It identifies possible constraints for Solution completion

Question 33

What is one of the dimensions of Lean-Agile Leadership?

Options:

A.

Emotional Intelligence

B.

Mindset and Principles

C.

Support organizational change

D.

Relentless improvement

Question 34

What is one approach to unlock the intrinsic motivation of knowledge workers?

Options:

A.

Centralize decision-making

B.

Provide autonomy

C.

Reduce work in process (WIP) limits

D.

Strive to achieve a state of continuous flow

Question 35

Which two statements describe an Agile Release Train? (Choose two.)

Options:

A.

It is the primary value delivery construct in the Scaled Agile Framework

B.

It is used to describe large system behaviors that fulfill Customer needs

C.

It shows the deliverables for the currently committed PI and offers visibility into the next two PIs

D.

It identifies when too much work is in the system which results in multitasking and frequent context switching

E.

It is a long-lived, self-organizing, virtual organization of 5 - 12 Agile Teams that plan, commit, and execute togethe

Question 36

Why is it important for teams to understand the optimum batch size for their work?

Options:

A.

To make value flow

B.

To complete more work

C.

To understand transaction costs

D.

To determine the correct cadence

Question 37

Which of the following activities does SAFe recommend as the first activity of the Inspect and Adapt event?

Options:

A.

Quantitative measurement

B.

PI System Demo

C.

Retrospective and problem-solving workshop

D.

Agreement on the problems to solve

Question 38

The CALMR approach to DevOps includes Automation, Lean flow, Measurement, and Recovery. What does the "C" represent?

Options:

A.

Cycle-time

B.

Cadence

C.

Continuous Integration

D.

Culture

Question 39

Which activity is key to successfully implementing the Scaled Agile Framework?

Options:

A.

Use the Innovation and Planning Iteration instead of the PI Planning process

B.

Replace the PI Planning process with the Inspect and Adapt workshop when possible

C.

Use a cadence-based PI Planning process

D.

Remove blocks such as portfolio estimation

Question 40

What is the first step in Kotter's 8-step process for leading change?

Options:

A.

Generate short-term wins

B.

Enlist a volunteer army

C.

Create a sense of urgency

D.

Build a guiding coalition

Question 41

Which statement correctly describes one aspect of the team's commitment at the end of PI Planning?

Options:

A.

A team commits to all the Features they put on the ART planning board

B.

A team commits only to the PI Objectives with the highest business value

C.

A team commits to all the Stories they put on their PI plan

D.

A team does not commit to uncommitted objectives

Question 42

What is one issue when organizing around functional silos?

Options:

A.

They do not provide development opportunities for employees

B.

Corporate responsibilities are not a focus

C.

They impede how value flows

D.

Operational activities are not included

Question 43

When should a component team be used?

Options:

A.

To develop T-shaped skills together with Continuous Integration

B.

To create each replaceable component with minimized dependencies

C.

To gain the fastest velocity with well defined interfaces

D.

To obtain high reuse and technical specialization with a focus on nonfunctional requirements

Question 44

What is one way to quickly address impediments to flow?

Options:

A.

Review burn-down charts

B.

Raise visibility of effects outside of ART control

C.

Identify them on the Planning Board

D.

Wait for the next Inspect and Adapt event

Question 45

Which basic Agile quality practice reduces bottlenecks & ensures consistency?

Options:

A.

Definition of Done

B.

Peer-review and pairing

C.

Collective ownership and standards

D.

Establish flow

Question 46

Which of the following statements is true about Roadmaps?

Options:

A.

Communicate intent

B.

Are commitment

C.

Are only adjusted at PI boundaries

D.

Provide a single planning horizon

Question 47

How does SAFe provide a second operating system that enables Business Agility?

Options:

A.

By achieving economies of scale

B.

By organizing around functional areas to focus on skills development

C.

By creating a hierarchy to provide stability

D.

By focusing on customers, products, innovation, and growth

Question 48

Which statement is true about the PI Planning event?

Options:

A.

It involves only the team members who are most qualified to estimate the work

B.

It involves program Portfolio Management to prioritize the Stories presented by teams during the final plan review

C.

It involves everyone in the program over a two-day period

D.

It involves Product Management and Product Owners on the first day and the rest of the teams on the second day

Question 49

On day two of PI Planning, management presents adjustments based on the previous day's management review and problem-solving meeting. What is one possible type of adjustment they could make?

Options:

A.

Create new User Stories

B.

Adjust business priorities

C.

Change a team's plan

D.

Redefine the length of the PI

Question 50

What is one of the five basic Agile quality practices applicable to all Agile Teams?

Options:

A.

Using non-functional requirements

B.

Creating the Architectural Runway

C.

Decentralized decision-making

D.

Shift learning left

Question 51

Which statement is true about uncommitted objectives?

Options:

A.

They help improve predictability

B.

They do not get assigned a business value score

C.

They are extra things the team can do if they have time

D.

The work to deliver uncommitted objectives is not planned into the Iterations during PI planning

Question 52

Team A is writing a Story enabling book shoppers to access their shopping cart from any page on the website. Which of the following examples represents the recommended user voice format for the Story?

Options:

A.

I am a book shopper that wants to access my shopping cart anywhere on the website

B.

I want to view my shopping cart so I can review what I am purchasing

C.

As a book shopper, I want access to my shopping cart from any page, so that I can review what I am purchasing

D.

As a book shopper, I want to access my shopping cart from any page

Question 53

What is used to describe functional and non-functional requirements?

Options:

A.

Milestones

B.

Architectural Runway

C.

Features

D.

Enablers

Question 54

What is a major benefit of reducing batch size?

Options:

A.

Increases visibility

B.

Decreases stress on the system

C.

Increases work in process

D.

Increases throughput

Question 55

During which PI Planning activity do Business Owners assign business value to PI Objectives?

Options:

A.

The final plan review

B.

The team breakout session

C.

The Management Review and Problem-Solving workshop

D.

The draft plan review

Question 56

What is one dimension of the Team and Technical Agility Core Competency?

Options:

A.

Relentless Improvement

B.

Innovation Culture

C.

Built in Quality

D.

Leading by Example

Question 57

Which statement is a principle of the Agile Manifesto?

Options:

A.

Measure everything

B.

Visualize and limit WIP, reduce batch sizes, and manage queue lengths

C.

Simplicity "the art of maximizing the amount of work not done" is essential

D.

Respect for people and culture

Question 58

When should new approaches be anchored in an organization's culture?

Options:

A.

Culture should not be changed because SAFe respects the current culture.

B.

Culture change comes right after a sense of urgency is created in the organization.

C.

Culture change comes last as a result of changing work habits.

D.

Culture change needs to happen before the SAFe implementation can begin.

Question 59

Why do Business Owners assign business value to team PI Objectives?

Options:

A.

To empower teams to make decisions around work

B.

To determine what the teams should work on first

C.

To override the decisions made in WSJS prioritization

D.

To ensure the teams do not work on architectural Enablers

Question 60

Which statement is true about pair work in the Scaled Agile Framework?

Options:

A.

It comes from pair programming in Extreme Programming (XP)

B.

It is a best practice that team members should spend 50% to 100% of the time in pair work

C.

It occurs during Iteration Planning

D.

It is for developers only

Question 61

During the final plan review, ART PI risks are ROAM'ed. What do the letters in ROAM represent?

Options:

A.

Resolved, Owned, Approved, Mitigated

B.

Resolved, Owned, Accepted, Mitigated

C.

Resolved, Owned, Assigned, Mitigated

D.

Resolved, Owned, Active, Mitigated

Question 62

Which statement is true about Features and Stories?

Options:

A.

Features should be small enough to fit into an Iteration

B.

Features can be larger than an Iteration but Stories should be small enough to fit into an Iteration

C.

They are prioritized by the team

D.

They are estimated like User Stories

Question 63

How does a team demonstrate progress?

Options:

A.

By presenting status slides

B.

By having the Product Owner verbally communicate to the stakeholders

C.

By showing the actual working product

D.

By showing screen shots of the product

Question 64

What is critical to improving flow?

Options:

A.

Frequent context switching

B.

Reduce the batch sizes of work

C.

Address the local problems

D.

Increase work in process (WIP) limits

Question 65

Which of the following categories addresses potential risks?

Options:

A.

Acquired

B.

Resolved

C.

Obtained

D.

Managed

Question 66

What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers", require besides purpose and minimum possible constraints?

Options:

A.

Autonomy

B.

Innovation

C.

Incentive-based compensation

D.

Transparency

Question 67

A decrease in variability leads to an increase in what?

Options:

A.

Autonomy

B.

Options

C.

Predictability

D.

Innovation

Question 68

What does the ART planning board show?

Options:

A.

Risks

B.

Significant dependencies

C.

Capacity and load

D.

Epics

Question 69

What is one key component of a Feature?

Options:

A.

Business plan

B.

Key stakeholders

C.

Release plan

D.

Benefit hypothesis

Question 70

Which of the Lean Thinking principles includes the activities from recognizing an opportunity through release and validation?

Options:

A.

Identify the Value Stream for each product

B.

Make value flow without interruptions

C.

Pursue perfection

D.

Precisely specify value by product

Question 71

What is the goal of the SAFe House of Lean model?

Options:

A.

Innovation

B.

Relentless Improvement

C.

Flow

D.

Value

Question 72

Which of the following Story components captures details on testing for completion?

Options:

A.

User voice

B.

Story map

C.

Acceptance criteria

D.

Release plan

Question 73

What is one action that occurs during iteration reviews for SAFe Scrum teams?

Options:

A.

Evaluating current state metrics

B.

Completing unfinished work

C.

Sizing unfinished stories

D.

Prioritizing unplanned work

Question 74

Which of the following team-level events does SAFe recommend running on a cadence during the PI for SAFe Team Kanban Teams?

Options:

A.

PO Sync

B.

Retrospective

C.

Coach Sync

D.

System Demo

Question 75

What type of information can be easily seen in a cumulative flow diagram?

Options:

A.

Time to complete a Feature

B.

Team capacity

C.

Work in process across the team

D.

The number of defects that escape to production

Question 76

What is one benefit of organizing around value, & reorganizing when required?

Options:

A.

Understanding the Portfolio Backlog

B.

Building the Continuous Delivery Pipeline

C.

Enabling a DevOps mindset

D.

Minimizing handoffs and dependencies

Question 77

What is typically included in the definition of done for the team increment?

Options:

A.

Stories are accepted by Product Management

B.

45 new questions addStories are accepted by the Product Owner

C.

Customer documentation is ready

D.

Regression testing is done

Question 78

Which of the following categories addresses potential risks?

Options:

A.

Resolved

B.

Obtained

C.

Supervised

D.

Acquired

Question 79

What is the focus of Lean Thinking?

Options:

A.

Reducing delays

B.

Implementing objective measures of progress

C.

Ensuring respect for people and culture

D.

Moving to an iterative development process

Question 80

A SAFe Portfolio is a collection of what?

Options:

A.

Development Value Streams

B.

Functional teams

C.

Solutions

D.

Business units

Question 81

What is one element teams present during the draft plan review?

Options:

A.

Iteration goals

B.

Planned business value

C.

Milestones

D.

ART PI risks