Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70special

Scrum PSM-I Professional Scrum Master I Exam Practice Test

Page: 1 / 27
Total 268 questions

Professional Scrum Master I Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$37.5  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$33  $109.99
Question 1

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

Options:

A.

True

B.

False

Question 2

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Developers.

D.

The Project Manager.

Question 3

True or False A scrum Master fulfills the same role as a traditional Project Manager

Options:

A.

True

B.

False

Question 4

How is management external to the Scrum Team involved in the Daily Scrum?

Options:

A.

The Scrum Master speaks on their behalf.

B.

The Development Team self-manages and is the only management required at the Daily Scrum.

C.

Management gives an update at the start of each Daily Scrum.

D.

The Product Owner represents their opinions.

Question 5

When is a Product Backlog item considered complete? (choose the best answer)

Options:

A.

When the item passes ail acceptance criteria

B.

When the item has gamed product sponsor approval

C.

At the end of the Sprint

D.

When the item meets the Definition of Done

Question 6

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

Options:

A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.

Question 7

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

Options:

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

Question 8

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Question 9

When is it most appropriate for a Scrum Team to change the Definition of Done?

(choose the best answer)

Options:

A.

During Product Backlog refinement.

B.

During the Sprint Retrospective.

C.

During Sprint Planning.

D.

Prior to starting a new project.

Question 10

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Question 11

Which statement best describes Scrum?

Options:

A.

A defined and predictive process that confirms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A cookbook that defines best practices for software development.

D.

A framework within which complex products in complex environments are developed.

Question 12

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

Options:

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, reporting to a chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Question 13

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.

Question 14

When must a scrum Team release each increment? (choose the best answer)

Options:

A.

when the Scrum Team finishes their work

B.

Alter every Sprint. without exception

C.

Whenever the product s tree of detects

D.

When it makes sense to release It.

Question 15

Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)

Options:

A.

The Stakeholders.

B.

The Product Owner.

C.

The Scrum Team.

D.

The Scrum Master.

E.

The Developers.

Question 16

Who determines how work is performed during the Sprint?

Options:

A.

Architects.

B.

The Development Team.

C.

The Scrum Master.

D.

Subject matter experts.

E.

Development Team managers.

Question 17

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Question 18

What is the key concern when multiple Development Teams are working from the same Product Backlog?

Options:

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

Question 19

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Question 20

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'

(choose the best answer)

Options:

A.

Never The entire Scrum Team is accountable for creating value every Sprint.

B.

At the Sprint Planning Evented

C.

Whenever a team member can accommodate more worn.

D.

During the Daily scrum

Question 21

Every Development Team should have:

Options:

A.

At least one representative from each major software engineering discipline (like QA, Dev, UX).

B.

The competencies and skills needed to deliver a Done Increment in a Sprint.

C.

One Lead Developer and no more than 8 other members.

Question 22

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Options:

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Question 23

Which does a self-organizing Development Team choose?

Options:

A.

Sprint length.

B.

How to best accomplish its work.

C.

Stakeholders for the Sprint Review.

D.

When to release, based on its progress.

E.

Product Backlog ordering.

Question 24

At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)

Options:

A.

If the stakeholders agree, the Product Owner can accept it and release it to the users.

B.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

C.

Review the item, add the “Done” part of the estimate to the velocity and create a Story for the remaining work.

D.

Do not include the item in the Increment this Sprint.

Question 25

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

Options:

A.

Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.

B.

Teach them that it is their responsibility to work with the other teams to create an integrated Increment.

C.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

D.

Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

Question 26

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Masters from each Scrum Team define a common Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

Question 27

Who is responsible for managing the progress of work during a Sprint?

Options:

A.

The Scrum Master.

B.

The Development Team.

C.

The Product Owner.

D.

The most junior member of the Team.

Question 28

How should a Development Team deal with non-functional requirements?

Options:

A.

Ensure every Increment meets them.

B.

Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.

C.

Handle them during the Integration Sprint preceding the Release Sprint.

D.

Assign them to the lead developers on the team.

Question 29

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Question 30

Which best describes the Product Backlog?

Options:

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Question 31

Which topics should be discussed in the Sprint Review?

Options:

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

Sprint results.

D.

All of the above.

Question 32

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog tor a Sprint to satisfy the stakeholders.

Options:

A.

True

B.

False

Question 33

A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?

Options:

A.

Add security to the definition of “Done”.

B.

Tell the Product Owner to stop further development of features until the issues are fixed.

C.

Create a Product Backlog item for security.

D.

Go check with the testers.

E.

Ask the person to share the issue with the team as soon as possible.

Question 34

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

Options:

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

Question 35

When is implementation of a Product Backlog item considered complete?

Options:

A.

At the end of the Sprint.

B.

When the item has no work remaining in order to be potentially released.

C.

When QA reports that the item passes all acceptance criteria.

D.

When all work in the Sprint Backlog related to the item is finished.

Question 36

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

Options:

A.

True

B.

False

Question 37

When multiple Scrum Teams are working on the same product, should all of their Increments be

integrated every Sprint? (choose the best answer)

Options:

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

No, that is tar too nard and must be done in a hardening Sprint

C.

No, each Scrum Team stands alone.

D.

Yes, in order to accurately inspect what is done.

Question 38

Which three of the following are true about Scrum? (Choose the best three answers.)

Options:

A.

Scrum implements self-management by replacing Project Managers with Scrum Masters.

B.

Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage

of Scrum to develop complex products.

C.

Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your

environment.

D.

Scrum is a framework for developing and sustaining complex products.

E.

Scrum is based on empiricism and lean thinking.

Question 39

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

Question 40

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

Options:

A.

True

B.

False

Question 41

Who creates a Product Backlog Item’s estimate?

Options:

A.

The Development Team after clarifying requirements with the Product Owner.

B.

The Product Owner with input from the Development Team.

C.

The most senior people in the organization, including architects and subject matter experts.

D.

The Scrum Master.

E.

The Development Team, alone.

Question 42

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

Options:

A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Question 43

Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)

Options:

A.

Definition of “Done”.

B.

How the team does its work.

C.

Team relations.

D.

The value of work currently represented in the Product Backlog.

E.

Arranging the Sprint Backlog for the next Sprint.

Question 44

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

Options:

A.

True

B.

False

Question 45

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

Options:

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Question 46

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Question 47

Who is responsible for collaboration with stakeholders?

(choose the best answer)

Options:

A.

The Business Analyst.

B.

The Scrum Team.

C.

The Team Manager.

D.

The Project Manager.

E.

The Developers.

Question 48

When is it most appropriate for a Scrum Team to change the definition of “Done”?

Options:

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Question 49

Sprint burndown charts are an efficient tracking tool, because they show:

Options:

A.

An estimate of the total work remaining for the Sprint.

B.

How much effort has gone into a Sprint.

C.

How many hours have been worked by each Development Team member.

D.

How many Product Backlog items remain.

Question 50

When does a Sprint conclude?

(choose the best answer)

Options:

A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Question 51

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

Options:

A.

Allow the Development Team to self-manage and determine for itself what to do.

B.

Set up the meeting and tell the Development Team that is how it will be done.

C.

Ask the Development Team members to alternate who is responsible for meeting setup.

D.

Inform management and ask them to solve it.

Question 52

What are two responsibilities of testers in a Development Team? (Choose two.)

Options:

A.

Verifying the work of programmers.

B.

Everyone in the Development Team is responsible for quality.

C.

Tracking quality metrics.

D.

Finding bugs.

E.

Scrum has no “tester” role.

Question 53

A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

Options:

A.

True

B.

False

Question 54

Which statement best describes a Product Owner’s responsibility?

Options:

A.

Optimizing the value of the work the Development Team does.

B.

Managing the project and ensuring that the work meets the commitments to the stakeholders.

C.

Directing the Development Team.

D.

Keep stakeholders from distracting the Development Team.

Question 55

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most

helpful in this situation?

(choose the best two answers)

Options:

A.

As a Scrum Team, prioritize the list and work on them in order.

B.

The Scrum Master discusses the impediments with the Scrum Team.

C.

The Product Owner should add the open impediments to the Product Backlog.

D.

Arrange a triage meeting with management.

Question 56

If burndown charts are used to visualize progress, what do they track?

Options:

A.

Accumulated cost.

B.

Individual worker productivity.

C.

Work remaining across time.

D.

Accumulated business value delivered to the customer.

Question 57

Who starts the Daily Scrum?

Options:

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Question 58

When does the next Sprint begin?

Options:

A.

When the Product Owner is ready.

B.

Immediately after the conclusion of the previous Sprint.

C.

The Monday following the Sprint Review.

D.

Immediately following the next Sprint Planning.

Question 59

A product Increment must be released to production at the end of each Sprint.

Options:

A.

True

B.

False

Question 60

Why should the Product Owner be present at the Daily Scrum?

Options:

A.

He/She doesn’t need to be there.

B.

To hear about impediments in functionality.

C.

To represent the stakeholders’ point of view.

D.

To participate as a Scrum Team member.

Question 61

User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?

(choose the best answer)

Options:

A.

Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

B.

The Developers on the Scrum Team should write the user documentation.

C.

Wait until you have a technical writer on your Scrum Team to take care of this.

D.

Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

Question 62

The Definition of Done serves which three purposes?

(choose the best three answers)

Options:

A.

Create a shared understanding of when work is complete.

B.

Guide the Developers on how many Product Backlog items to select for the

Sprint.

C.

Increase transparency.

D.

Describe the work that must be mostly done before the Sprint is allowed to end.

E.

Describe the purpose, Objective, and timebox Of each Scrum event.

Question 63

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

Options:

A.

Consulting with the Development Team.

B.

Prioritizing the list and working on them in order.

C.

Arranging a triage meeting with all project managers.

D.

Alerting management to the impediments and their impact.

Question 64

What are two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Finding bugs.

B.

Tracking quality metrics.

C.

Verifying the work of programmers.

D.

Scrum has no "tester" role.

E.

The Developers are responsible for quality.

Question 65

The Scrum Team should have all the skills needed to:

(choose the best answer)

Options:

A.

Turn Product Backlog items into a valuable, useful Increment.

B.

Do all of the development work, except for specialized testing that requires additional

tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Question 66

You are the Scrum Master of a new, to be developed product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

Options:

A.

How will we make sure all teams have the right amount or expertise?

B.

What is the right mixture of senior and junior people on each team?

C.

Who are going to be the team leads?

D.

Who are the subject matter experts on each team?

Question 67

Who creates the definition of “Done”?

Options:

A.

The Scrum Master as he/she is responsible for the Development Team’s productivity.

B.

The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.

C.

The Product Owner as he/she is responsible for the product’s success.

D.

The development organization (or Development Team if none is available from the development organization).

Question 68

True or False: Multiple scrum Teams working on the same product must have the same Sprint start date.

Options:

A.

True

B.

False

Question 69

Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)

Options:

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a subject matter expert in the Scrum Team.

C.

False. A Scrum Master is only required when asked for by the Scrum Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Question 70

Who should know the most about the progress toward a business objective or a release?

Options:

A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Question 71

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

Options:

A.

A proportional amount of time on analysis, design, programming, testing, and documentation.

B.

As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.

C.

All development work and at least some testing.

D.

As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”.

Question 72

When is the Sprint Backlog created?

Options:

A.

At the beginning of the project.

B.

During the Sprint Planning meeting.

C.

Prior to the Sprint Planning meeting.

D.

During the Sprint.

Question 73

The Product Backlog is ordered by:

Options:

A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.

Question 74

During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)

Options:

A.

Facilitate inspection and adaptation opportunities as requested or needed

B.

Coaching the team members in self-management

C.

Ensure the Product Owner attends all scrum events.

D.

Escalate team conflicts to functional line managers

E.

Monitor the progress of the Developers

F.

Assign tasks with the Scrum team.

Question 75

What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)

Options:

A.

There is no such thing as Sprint 0.

B.

Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.

C.

Make the complete project plan to commit date, budget, and scope to the stakeholders.

D.

Determine the composition of the Development Teams so they have the capacity to deliver the completed

forecast.

E.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

Question 76

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

Options:

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the people doing the work.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Question 77

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

Options:

A.

By ensuring the meetings start and end at the proper time.

B.

By removing impediments that hinder the Development Team.

C.

By facilitating Development Team decisions.

D.

By keeping high value features high in the Product Backlog.

Question 78

What may be included in the Sprint Backlog? (choose the best answer)

Options:

A.

User Stones

B.

Tasks

C.

Use Cases

D.

Tests

E.

Any of the above (or others) which ate a decomposition of the selected Product Backlog items

Question 79

What is the role of management in Scrum?

Options:

A.

To facilitate the Scrum Teams with insights and resources that help them improve.

B.

To monitor the Development Team’s productivity.

C.

To identify and remove people that aren’t working hard enough.

D.

To continually monitor staffing levels of the Development Team.

Question 80

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

Options:

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Page: 1 / 27
Total 268 questions