Weekend Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: suredis

SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Exam Practice Test

Page: 1 / 17
Total 165 questions

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$42  $119.99

PDF Study Guide

  • Product Type: PDF Study Guide
$36.75  $104.99
Question 1

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

This assignment can then be used to display the planned costs of the orders of the project

B.

This assignment can then be used to display the unit costs of the orders of the project

C.

It can be copied to a new project

D.

Cost planning can be moved automatically along with the activities

Question 2

In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?

Please choose the correct answer.

Response:

Options:

A.

Available to promise check

B.

Available on booking check

C.

Available on requirement check

D.

Immediate delivery check

Question 3

Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?

There are 3 correct answers to this question.

Response:

Options:

A.

WBS element

B.

Assignment

C.

Network header

D.

Network activity

Question 4

How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers?

Please choose the correct answer.

Response:

Options:

A.

Standard overview

B.

Capacity detail list

C.

Variable overview

D.

Tabular overview

Question 5

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?

Please choose the correct answer.

Response:

Options:

A.

Deviations

B.

Time gaps

C.

Floats

D.

High priority

Question 6

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

Options:

A.

Periodic settlement

B.

Full settlement

C.

Profile settlement

D.

Overview settlement

Question 7

When using budgeting and active availability control, which business transactions affect the current budget?

There are 3 correct answers to this question.

Response:

Options:

A.

Cost element planning

B.

Original budget

C.

Revenues

D.

Transfers

E.

Supplements

Question 8

Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *

Options:

A.

Priority of Events must be set

B.

Event Scenarios must be defined

C.

Scheduling Paramaters for Material Scheduling must be set

D.

Events must be released manually

Question 9

While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?

Please choose the correct answer.

Response:

Options:

A.

Scheduling forwards

B.

Scheduling backwards

C.

Variances

D.

Scheduling baseline, planned and forecast

Question 10

Which of the following are controlled using plant and order type parameters?

There are 2 correct answers to this question.

Response:

Options:

A.

Number assignment

B.

If the network is assigned to an activity or header

C.

Default value settings

D.

The settlement rule strategy

Question 11

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

Response:

Options:

A.

The system status created is active.

B.

The system status master data locked is activate.

C.

You are not the responsible person for that WBS element.

D.

The confirmation exceeds the budget assigned to the WBS.

Question 12

What is copied when transferring a simulation version back to an operative project?

There are 3 correct answers to this question.

Response:

Options:

A.

Plan costs

B.

WBS elements

C.

Actual work

D.

Maintenance orders assigned to the project

E.

Network activities

Question 13

Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?

Please choose the correct answer.

Response:

Options:

A.

Overheads costing

B.

Planned costing

C.

Profitability costing

D.

Activity based costing

Question 14

Which account assignment category is important for non-valuated project stock with WBS and sales order item?

Please choose the correct answer.

Response:

Options:

A.

E = quantities and values managed in the sales order item

B.

D = quantities managed using sales order item and values managed in projects

C.

G = plant stock, values managed using projects

D.

Q = quantities and values managed in projects

Question 15

How do you optimize cash flows to maximize project profits and reduce project costs?

Please choose the correct answer.

Response:

Options:

A.

PS Cash management

B.

Mile stone billing

C.

Milestone management

D.

Billing plan

Question 16

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

Options:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Question 17

What is the transaction code for editing the planning profile?

Please choose the correct answer.

Response:

Options:

A.

OPSS

B.

OPDS

C.

OPSB

D.

OPSC

Question 18

Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?

Please choose the correct answer.

Response:

Options:

A.

Preliminary purchase requisition

B.

Planned independent requirement

C.

Planned purchase requisition

D.

Third party purchase requisition

Question 19

Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors?

Please choose the correct answer.

Response:

Options:

A.

Work center and planned work

B.

Work center and activity

C.

Activity and task

D.

Work center and vendor

Question 20

Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.

In this scenario planned costs are determined for which of the following?

There are 3 correct answers to this question.

Response:

Options:

A.

Primary costs for general costs activities

B.

Primary costs for material components

C.

Primary costs for service activities

D.

Activity inputs for internally-processed activities

Question 21

Which of the following determines the item category assigned in the sales documents?

There are 2 correct answers to this question.

Response:

Options:

A.

Sales document type

B.

Schedule line items

C.

Material pricing group

D.

Material item category group

Question 22

Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile?

Please choose the correct answer.

Response:

Options:

A.

Proj.summ.master data indicator

B.

Project summarization indicator

C.

Capacity requirement indicator

D.

Version profile indicator

Question 23

A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?

There are 2 correct answers to this question.

Response:

Options:

A.

Define Layout Detail Screen for WBS to specify customer-specific tabs.

B.

Define Create User-Defined Fields for WBS to specify the mandatory fields.

C.

Define Field Selection for WBS to specify the mandatory fields.

D.

Define Table Settings for WBS to specify customer-specific tabs.

Question 24

In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?

There are 2 correct answers to this question.

Response:

Options:

A.

Project view

B.

Resource view

C.

Work center view

D.

Assignment view

Page: 1 / 17
Total 165 questions