Which product records any project outcomes perceived as negative by stakeholders?
In what process is the authorization to deliver the project's products given?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Which is an objective of the Managing Product Delivery process?
Which is NOT a purpose of a Benefits Review Plan?
What takes place during the Closing a Project process?
Which plan provides the Business Case with costs during the Initiating a Project process?
What is the definition of a project outcome?
Which should be funded by a change budget?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Which should be funded from a change budget?
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Which is a typical core activity within configuration management?
Which is a purpose of the Controlling a Stage process?
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
What is the collective name for individuals or groups who may be affected by a project?
Which is an objective of the Closing a Project process?
Which is one of the six aspects of project performance that needs to be managed?
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
Which is an objective of the Directing a Project process?
Which does NOT reflect the PRINCE2 principle of continued business justification?
Which is a purpose of the Managing Product Delivery process?
Which is a purpose of the Initiating a Project process?
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Which is NOT considered when defining risk tolerance?
Which product identifies how often stakeholders require information?
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
Which should be provided by a project mandate?
Which is an objective of the Starting up a Project process?
Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
Which describes a risk effect?
Which is a responsibility of a risk owner?
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
Which control must be used as a minimum requirement for applying the 'progress' theme?
Which is a purpose of a Project Product Description?
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
Which is a purpose of the 'initiating a project' process?
Who is responsible for documenting any tailoring of the business case theme?
How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?
Which describes a time-driven control?
Which statement about stages is true?
Which is a minimum requirement for applying the organization theme?
How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Which is a purpose of the change theme?
What is the change authority role permitted to authorize?
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?