Summer Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

PMI PMI-SP PMI Scheduling Professional Exam Practice Test

Page: 1 / 32
Total 323 questions

PMI Scheduling Professional Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$43.75  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$38.5  $109.99
Question 1

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Options:

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Question 2

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Options:

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Question 3

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Options:

A.

Three days

B.

One day

C.

Four days

D.

Zero days

Question 4

Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?

Options:

A.

It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.

B.

They likely do not understand the SPI formula.

C.

It is not good news, as the number should be closer to 100 than 0.

D.

It is good news, but Mark may have large cost variances to achieve this value.

Question 5

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Options:

A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Question 6

Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?

Options:

A.

PV/EV

B.

EV-AC

C.

EV-PV

D.

EV/PV

Question 7

What is the term assigned to graphic in the figure given below?

Options:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Question 8

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Options:

A.

1.07

B.

0.98

C.

0.89

D.

Ten percent

Question 9

Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

Options:

A.

Functional manager

B.

Operations manager

C.

Project manager

D.

Seller

Question 10

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

Options:

A.

It is a report that details the current status of risks and issues.

B.

It is a software application that allows stakeholders to view the project manager's performance.

C.

It is a web-based tool to inspect the project deliverables for performance.

D.

It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.

Question 11

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.923

B.

1.083

C.

1.261

D.

0.792

Question 12

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Options:

A.

Scope Verification

B.

Configuration Management System

C.

Project Management Information System

D.

Integrated Change Control

Question 13

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

Options:

A.

Resource calendars

B.

Schedule data

C.

Activity list

D.

Project scope statement

Question 14

Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

Options:

A.

Project charter

B.

Scope of statement

C.

SOW

D.

WBS

Question 15

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

Options:

A.

Work performance measurement

B.

Stakeholder expectation management

C.

Project communication management

D.

Stakeholder analysis

Question 16

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

Options:

A.

1.02

B.

0.98

C.

0.90

D.

-$108,120

Question 17

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

Options:

A.

Parametric estimate

B.

Definitive estimate

C.

Analogous estimate

D.

Bottom-up estimate

Question 18

John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

What is the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.96

B.

1.082

C.

0.833

D.

1.0625

Question 19

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

Options:

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Question 20

Which of the following statements best describes an activity in a project?

Options:

A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.

B.

It is the effort needed to complete a work package.

C.

It is the unit of resource utilization needed to complete a project deliverable.

D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Question 21

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

Options:

A.

300

B.

50

C.

600

D.

25

Question 22

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

Options:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Question 23

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Options:

A.

Critical path method

B.

Schedule management plan

C.

Scheduling tool

D.

Critical chain method

Question 24

Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

WBS

D.

Enterprise environmental factors

Question 25

You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?

Options:

A.

Activity attributes

B.

Activity list

C.

Project scope statement

D.

Milestone list

Question 26

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

Options:

A.

Scope change control

B.

Schedule change control

C.

Integrated change control

D.

Change Control Board approval process

Question 27

What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?

Options:

A.

Judgmental methods

B.

Time series method

C.

Ensemble forecasting

D.

Causal/econometric method

Question 28

You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?

Options:

A.

Activity attributes

B.

Project management plan

C.

Schedule Management Plan

D.

Roles and Responsibilities Matrix

Question 29

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Options:

A.

It is derived from the constraints of the project.

B.

It is assigned to the project by management.

C.

It is created by the stakeholders.

D.

It is developed from the schedule network analysis.

Question 30

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options:

A.

Resource competition

B.

Matrix organization

C.

Resource requirement

D.

Resource constraint

Question 31

Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?

Options:

A.

The activities to be crashed must have additional quality control metrics associated with them.

B.

The activities to be crashed cannot be of fixed duration.

C.

The activities to be crashed cannot have risks associated with them greater than 0.80.

D.

The activities cannot be on the critical path in order to be crashed.

Question 32

You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?

Options:

A.

Amount of buffer remaining to the amount of resources available

B.

Amount of buffer remaining to the amount of buffer used

C.

Availability of project resources and project buffer

D.

Amount of buffer needed to the amount of buffer remaining

Question 33

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

Options:

A.

Schedule data

B.

Work performance information

C.

Project management plan

D.

Project schedule

Question 34

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?

Options:

A.

19

B.

24

C.

29

D.

46

Question 35

You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?

Options:

A.

Scope management plan

B.

Performance management plan

C.

Communications management plan

D.

Project management plan

Question 36

A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?

Options:

A.

As workers complete the installation, efficiency will increase and durations will decrease.

B.

As workers complete the installation, errors and risks will increase the actual completion.

C.

As workers complete the installation, effort will diminish and efficiency will decrease.

D.

As workers complete the installation, labor will diminish so duration will increase.

Question 37

You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

Options:

A.

284,635

B.

570,025

C.

569,270

D.

755

Question 38

Which of the following is an output of the Identify Stakeholders process?

Options:

A.

Scope baseline

B.

Project scope statement

C.

Project charter

D.

Stakeholder register

Question 39

Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?

Options:

A.

Stakeholder assessment information

B.

Stakeholder register

C.

Communications management plan

D.

Stakeholder management strategy

Question 40

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

Options:

A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Question 41

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

Options:

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Question 42

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

Options:

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Question 43

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

Options:

A.

$227,140

B.

0.75

C.

0.95

D.

-$56,789

Question 44

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

Options:

A.

Scope baseline

B.

Activity attributes

C.

Activity list

D.

Activity resource requirements

Question 45

John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Hammocks

B.

Critical path scheduling

C.

Flags

D.

Tasks

Question 46

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Question 47

Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?

Options:

A.

Thomas

B.

Sarah

C.

Each of the team leaders for the eight virtual teams

D.

Beth

Question 48

What is the formula to find the schedule performance index?

Options:

A.

EV-PV

B.

EV/AC

C.

EV/PV

D.

EV-AC

Page: 1 / 32
Total 323 questions