Summer Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Exam Practice Test

Page: 1 / 23
Total 227 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$43.75  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$38.5  $109.99
Question 1

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account.

 

Question 2

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact

 

Question 3

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Options:

A.

Update the assumptions/exclusions register

B.

Hire more resources and crash the schedule

C.

Perform a qualitative risk analysis for the project

D.

Mitigate risks identified on the sensitivity analysis

Question 4

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Question 5

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.

Adopt a predictive approach to manage the risks.

B.

Adopt agile approaches to manage the risks.

C.

Utilize proper documentation to help manage the risks.

D.

Conduct weekly risk management meetings with all stakeholders.

Question 6

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

 

Question 7

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.

Perform a probability and impact assessment

B.

Perform Monte Carlo simul-ations

C.

Perform a sensitivity analysis

D.

Perform a risk data quality assessment

Question 8

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Question 9

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Question 10

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Question 11

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Question 12

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Question 13

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Question 14

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Question 15

A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

Options:

A.

Escalate this initiative to project decision makers and sponsors.

B.

Accept the fact that there is a risk associated with this new technology.

C.

Take advantage of this opportunity of Improving the project performance.

D.

Outsource the implementation of the new technology as soon as possible.

Question 16

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?

Options:

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

Question 17

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.

B.

Improve monitoring and controlling of activities.

C.

Document the issues in the lessons learned.

D.

Create an issue log to share with the team.

Question 18

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements

B.

Monte Carlo analysis from a similar project

C.

List of pre-approved contractors

D.

Organization chart for city permit department

E.

Risk management plan

Question 19

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

Question 20

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Options:

A.

Immediately hire as soon as the project begins to fall behind schedule.

B.

Hire as soon as the project metrics trigger a risk response.

C.

Only hire when it is economically feasible to do so.

D.

Only hire if risk response is escalated and approved by the stakeholders.

 

Question 21

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Options:

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Question 22

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Question 23

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Question 24

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Question 25

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simul-ation

C.

The full risk description

D.

The risk response plan

Question 26

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W&S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Question 27

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

B.

React to the secondary and residual risks only if they occur.

C.

Include secondary and residual risks as part of the response.

D.

Transfer secondary and residual risks to the project sponsor.

Question 28

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.

Process the freight invoices at higher shipping costs against the project's contingency allowance.

B.

Request a formal change order from the customer to increase the project's total budget.

C.

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.

Ask the project sponsor to cover the additional shipping costs on the company's reserves account.

Question 29

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

Options:

A.

Quantitative risk analysis

B.

Force field analysis

C.

Qualitative risk analysis

D.

Stakeholder analysis

Question 30

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.

Include all stakeholders in the project's governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders' tolerance.

D.

Consider stakeholders' positions and opinions regarding the project’s output.

Question 31

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

Options:

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Question 32

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Question 33

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

Options:

A.

Mitigate

B.

Accept

C.

Enhance

D.

Exploit

Question 34

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Question 35

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team

 

Question 36

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability

 

Question 37

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

Options:

A.

Enhance risk identification.

B.

Review the contingency reserves.

C.

Create a risk response plan.

D.

Review the risk registry.

Question 38

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores

 

Question 39

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.

Time Series Analysis

B.

Regression Analysis

C.

Variance Analysis

D.

Monte Carlo Analysis

 

Question 40

A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

Options:

A.

Sensitivity analysis

B.

Qualitative analysis

C.

Statistical analysis

D.

Impact analysis

 

Question 41

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Question 42

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Question 43

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Question 44

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

Options:

A.

Update the watchlist.

B.

Initiate a risk response when these risks occur.

C.

Address only the high-priority risk.

D.

Perform a risk urgency assessment.

 

Question 45

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration.

 

Question 46

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Question 47

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Question 48

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Question 49

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

Question 50

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

Question 51

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager

Question 52

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?

Options:

A.

Check the schedule for constraints

B.

Use the P90 date on the risk report

C.

Decrease the number of iterations

D.

Decrease the risk consequences

Question 53

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Question 54

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

 

Question 55

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.

Earned value analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Root cause analysis

Question 56

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis.

 

Question 57

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

Options:

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager's project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

Question 58

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks

 

Question 59

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

Options:

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

Question 60

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

 

Question 61

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan

 

Question 62

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simul-ation

Question 63

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.

B.

Review the effectiveness of the risk process.

C.

Update the risk management plan.

D.

Escalate the project risks to upper management.

 

Question 64

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Question 65

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks' severity, and update the risk register.

Question 66

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.

The risk identification process can be carried out as long as the project statement is available.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

Question 67

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Question 68

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks.

 

Page: 1 / 23
Total 227 questions