Summer Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

PMI PMI-200 PMI Agile Certified Practitioner (PMI-ACP) Exam Practice Test

Page: 1 / 48
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$43.75  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$38.5  $109.99
Question 1

An agile team member identifies a potential problem within the project team How should the team's coach react?

Options:

A.

Document the problem, escalate to the project manager and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Question 2

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.

What should the team do to improve the accuracy of their estimates?

Options:

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint.

D.

Begin tracking estimated effort metrics as an input to performance evaluation

Question 3

The initial roadmap and release dates for an agile project were set based on data from similar projects and some expert opinions. Halfway through the project, however, the team’s estimates are different. Based on the team’s velocity, two more iterations were necessary to accomplish the initial scope.

How should the agile lead explain the difference to the project sponsor?

Options:

A.

Explain how many scope changes were requested by the product owner and how many hours the team dedicated to unplanned tasks.

B.

Explain that initial estimates help measure project feasibility but the real estimates depend on how much the team learns in each sprint.

C.

Explain some features and requirements made aspects of the project unique and are not comparable to previous experiences.

D.

Explain the list of materialized risks not considered at the beginning of the project ted to extra work hours and costs.

Question 4

A new project is under way and the team is using the Kanban method. One of the team members raised a specific issue related to a programming language that the team member faced in previous projects.

What should the project leader do to handle the issue?

Options:

A.

Include the issue in the risk log.

B.

Monitor the issue in a notation system.

C.

Ask the team member to take full ownership of the issue.

D.

Advise the team member to add the issue to the board.

Question 5

Two similar stories A and B are estimated at 3 story points. Story C, is estimated at 8 points After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points so to provide a better estimate

B.

Add points to story B's iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A; B and C

Question 6

An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.

What can the agile team do to improve value delivery in the absence of a true user?

Options:

A.

Improve the velocity of each iteration.

B.

Add a variety of skilled programmers and expert testers to the team.

C.

Reduce the length of each iteration.

D.

Add a variety of users, such as business analysts and domain experts, to the team.

Question 7

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Question 8

Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?

Options:

A.

Use an information radiator to help increase the transparency of work for key stakeholders.

B.

Send status updates whenever the stakeholders request them.

C.

Hold Scrum meetings more frequently to ensure stakeholders are well informed.

D.

Instruct the team to focus on their own assignments rather than the work of others.

Question 9

Conversation transcript between the customer and the product owner (PO):

Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.

PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?

Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?

PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?

Customer: I own an Android phone, but I also need integration with the Apple phones.

Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)

Options:

A.

Monthly calendar view

B.

Android phone integration

C.

Windows end of support deadlines

D.

Vacation calendar for team members

E.

Scheduler to add events

F.

Product increment release dates

Question 10

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team's velocity drops.

Question 11

On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders requirements.

Which of the following could help resolve the incomplete work?

Options:

A.

Conduct a spike so that the team can focus on defect repair without the distraction of new work items.

B.

Create a burndown chart to ensure the team understands the variance between the current and target velocity

C.

Work with the product owner to reduce the complexity of the work so that the team can improve quality.

D.

Work with the team to ensure that acceptance criteria is being properly defined and understood.

Question 12

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team's agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Question 13

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Question 14

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Question 15

More details for a story are required before the upcoming sprint planning meeting What should the scrum master do?

Options:

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Question 16

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team's time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Question 17

After some iterations, the agile practitioner observes that the team is self-organizing in small knowledge silos. Which action should be taken regarding the team's behavior?

Options:

A.

Raise the concern to upper management.

B.

Establish rules for the team to avoid this situation.

C.

Reorganize the team aiming to force the behaviors.

D.

Advise the team of the risks and invite them to change.

Question 18

On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?

Options:

A.

A project charter should be established and reviewed throughout the project life cycle to ensure the accurate documentation of stakeholders' interests and expectations.

B.

A product backlog should be created to list the project requirements from all of the project stakeholders.

C.

An Agile Manifesto should be created to document the project stakeholders, their desired outcomes, and identified risks.

D.

A user story should be created for all key stakeholders to list their individual business objectives and needs.

Question 19

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Question 20

Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.

What should the scrum master do to handle this situation?

Options:

A.

Separate large user stories.

B.

Apply work-in-progress limits.

C.

Organize user stories into epics.

D.

Replace user stories into features.

Question 21

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

Options:

A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Question 22

Based on the backlog metrics in the chart what can explain the jump in points at the end of iteration 4?

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with thatwork.

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Question 23

During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Question 24

How can a project team effectively work toward a common goal and communicate as they scale and expand to build a new business-critical platform, given that they have been responsible for a small customer-facing product with little complexity over the past 2 years?

Options:

A.

Daily coordination meeting

B.

Instant messaging tools

C.

Web conferencing

D.

Work collaboration platform

Question 25

An agile facilitator is helping a team. The team is taking too long in each daily coordination meeting, and the facilitator is beginning to view the time as unproductive.

What should the agile facilitator do to help the team?

Options:

A.

Reduce the number of participants in the daily coordination meeting so only one representative for each user story or area of expertise can participate each day.

B.

Change the structure of the daily coordination meetings so team members only comment on the blockers they face during the day.

C.

Let team members decide how to execute the meeting because they are self-organized and should know what works for them.

D.

Pay attention to the comments of each team member during the meeting and intervene every time they deviate from the objective of the meeting.

Question 26

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Question 27

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

Options:

A.

Address this impediment by obtaining suitable training for the team.

B.

Address the risks resulting from complexity within sprint zero.

C.

Facilitate team brainstorming of the risks resulting from complexity for the risk register.

D.

Motivate the team to try new technical approaches.

Question 28

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Question 29

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

Options:

A.

Coordinate a collaboration session so all the team members are involved in the solution process.

B.

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.

Hire external consultants to advise on solution options and train team members in any technical gaps.

Question 30

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Question 31

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer How should the team resolve this?

Options:

A.

Refer to the values of the agile framework and the team

B.

Review the signed customer contract

C.

Check the sprint priority list

D.

Submit the problem to the product owner

Question 32

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

Options:

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Question 33

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

Question 34

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Question 35

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Question 36

A project is to be started with a team of nine existing and nine new members. The scrum master feels that the team is too large and wants to break it into three teams. The scrum master sets aconstraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the scrum master do to accomplish this?

Options:

A.

Ask the team members' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the scrum master.

Question 37

The product owner is very concerned about work not being completed and tested before a hard release date. What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Question 38

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Options:

A.

Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk.

B.

The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions.

C.

Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support.

D.

An owner should have been identified to obtain timely stakeholder feedback.

Question 39

The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.

What is the estimated project conclusion?

Options:

A.

Twelve months

B.

Three months

C.

Six months

D.

Two months

Question 40

Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?

Options:

A.

Organize onsite backlog-refinement workshops to ensure common understanding.

B.

Set up weekly meetings where all team members will participate.

C.

Call an onsite meeting where ground rules will be discussed and agreed upon.

D.

Ask the product owner to prepare an onsite team-building activity.

Question 41

An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

Options:

A.

Communicate the importance of the business need to the team and refine the product backlog.

B.

Ask the team to discuss the changes to the features with the customer.

C.

Meet with the agile team lead to prioritize the requirements.

D.

Discuss and prioritize the requirements with the team.

Question 42

Which option describes how risk should be managed in an agile project?

Options:

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stones they have been assigned

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Question 43

A senior team member feels underutilized. What should the agile practitioner do?

Options:

A.

Transfer the senior member to another team that will more fully utilize their skill set.

B.

Conduct a performance evaluation to determine whether or not this member is a team player.

C.

Encourage the project team to involve the senior member in more project activities.

D.

Ask the functional manager to determine the best course of action.

Question 44

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Question 45

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

Options:

A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Question 46

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

Options:

A.

Interactive communication

B.

Pull communication

C.

Interpersonal communication

D.

Push communication

Question 47

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance. How should the agile practitioner handle the recommendation?

Options:

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team's senior members decide whether to adopt the suggested practice.

Question 48

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Question 49

A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?

Options:

A.

Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.

B.

Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.

C.

Plan a transformation to agile delivery methods for senior leadership before starting project implementation.

D.

Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.

Question 50

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.

What should the scrum master do?

Options:

A.

Explain to the SME the importance of being a team player, that the tasks are assigned by the scrum master, and work should not be refused.

B.

Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist.

C.

Leverage a separate testing team altogether to assist with all testing to ensure consistent results.

D.

Explain to the team the importance of reducing team size by reducing specializations and bottlenecks and that every team member plays an equal part.

Question 51

While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)?

Options:

A.

How much risk is needed to develop an MMF

B.

How much money the organization will earn or save by having the MMF

C.

How many stakeholders are influencing the MMF

D.

How much time does an organization need to develop an MMF

Question 52

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

Options:

A.

Organize separate meetings with each individual team member.

B.

Create a safe environment for discussions during meetings.C Emphasize rules that need to be respected during meetings

C.

Allow team members to talk when they feel comfortable without any pressure.

Question 53

A project team realizes that an important task on the iteration backlog will take more time than originally estimated What should the project team do?

Options:

A.

Continue working on the task until it is completed

B.

Remove the task owner from the project team

C.

Add resources to reduce time to task completion

D.

Stop working on the task and include it in the next iteration

Question 54

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?

Options:

A.

Plan for the second release to include regulatory changes and new features.

B.

Hold off making changes during the current release because the regulatory changes cannot be planned for.

C.

Verify the team is building the product in increments which can be adapted at the last minute if necessary.

D.

Monitor regulatory discussions to get a head start on the upcoming regulatory changes.

Question 55

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Question 56

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Question 57

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Question 58

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

Options:

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Question 59

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

Options:

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Question 60

A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company. What should the agile coach ensure that developers do?

Options:

A.

Establish pair programming partners, and regularly perform peer reviews.

B.

Perform demos at the end of each iteration.

C.

Send coding to the quality assurance (QA) team upon completion.

D.

Demonstrate each feature to the client as soon as coding is complete.

Question 61

A client states that a product is not being built as requested How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Question 62

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.

What should the agile practitioner do?

Options:

A.

Review established ground rules with the team

B.

Ask team members specific questions to identify the cause

C.

Encourage the team to continue working to maintain the iteration's schedule

D.

Meet with the product owner and stakeholders to discuss the issue

Question 63

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Question 64

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release.

What should the agile coach do?

Options:

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Question 65

An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?

Options:

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand ups

D.

Post a project board in an area where all can view it

Question 66

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.

What should the product owner do to resolve this?

Options:

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project's validity.

Question 67

Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?

Options:

A.

Understand the physical and virtual communication needs of the team and plan agile events based on the majority of the team members' needs.

B.

Escalate with senior management and ensure that everyone on the project team is physically colocated for all planned agile events.

C.

Invest in technology-collaboration tools to enable effective communication and ensure a common understanding of the scope, issues, and solutions.

D.

Recognize the different communication styles of the stakeholders and take a vote on the best approach that will work for the team.

Question 68

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

Options:

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company's profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Question 69

A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project.

What should the project leader suggest?

Options:

A.

Develop and document a detailed architectural design: peer review with the development team and implement/test

B.

Develop the functional requirements of the solution first before any non-functional requirement, as they provide morecustomer value

C.

Discuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature

D.

Develop and test the implementation approach and demonstrate it at the next sprint review to collect feedback

Question 70

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

Options:

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Question 71

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

Options:

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Question 72

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Question 73

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Question 74

What should a Scrum Master do when one team member falls behind in their tasks?

Options:

A.

Move the task to another team member who has spare capacity in the sprint

B.

Ask the team for suggestions

C.

Privately offer the team member encouragement to meet task commitments

D.

Notify the product owner.

Question 75

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Question 76

An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.

What should the agile practitioner do?

Options:

A.

Suggest that all agile teams share weekly reports on their projects.

B.

Encourage the team to independently find a solution.

C.

Work with the team to create a solution for disseminating team knowledge throughout the company.

D.

Recommend hiring an external expert to advise on the best methods for sharing knowledge among teams.

Question 77

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Options:

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

Question 78

A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope What should the scrum master do?

Options:

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Question 79

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)

Options:

Question 80

During a team meeting members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation. What should the agile practitioner do?

Options:

A.

Organize a team-building activity to improve team morale

B.

Have team members work in pairs to learn from each other and develop new skills

C.

Ask team members to perform a value stream analysis of their activities.

D.

Add more resources to the team to help with the tasks

Question 81

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Question 82

A project manager is working on a database migration project to cloud services (Refer to Migration Strategy to Cloud Services table). The project team has accumulated significant technical debt over several sprints due to pressure to deliver features quickly. This debt is nowimpacting their ability to deliver new features, leading to a notable decline in product performance and customer satisfaction.

Identify the actions the team should take to effectively manage technical debt while consistently delivering high-value features that align with stakeholder expectations.

Options:

A.

Form a separate learn dedicated lo handling technical debt, allowing the current team to focus on new features to maintain a competitive advantage and stakeholder satisfaction.

B.

Include technical debt tasks in every sprint, treating them with the same level of priority as new features, and continuously review the impact on the project's overall goals.

C.

Ignore the technical debt foe now and focus exclusively on delivering new features so that the project can maintain a competitive advantage and stakeholder satisfaction.

D.

Dedicate multiple consecutive sprints solely to addressing technical debt, halting new feature development temporarily to minimize the impact on the project's overall goals.

Question 83

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?

Options:

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Question 84

Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?

Options:

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

Question 85

In a project, the customer asks for a requirement that clearly deviates from the contract terms. How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Question 86

The project lead of a newly created agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Question 87

A product owner needs to elaborate on a product roadmap. How can the product owner collaborate with stakeholders to identify the features that offer maximum value?

Options:

A.

Identify the product users and their high-level key activities to get their perspective because the product is intended for them.

B.

Obtain the project sponsor's perspective to get an initial idea of the features they believe the product should have to guide the development team.

C.

Analyze the development team's capacity and skills because these will determine which features to include in the roadmap.

D.

Create a draft of the product roadmap that the development team can use as a guide for further guidance.

Question 88

A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.

Which action should the scrum master take to resolve this situation?

Options:

A.

Mitigate the new conflicts that appear and rely on the self-organization of the team.

B.

Escalate the issue to senior management to make a decision.

C.

Follow the organization's policies to remove the team member to boost team engagement.

D.

Attend daily coordination meetings and retrospectives with the agile coach.

Question 89

During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

Options:

A.

Inform the product owner's manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Question 90

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.

B.

Ask the team to find a workaround so that they can continue with the current project management plan.

C.

Advise the team to continue working on the sprints as the release plan has been set.

D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.

Question 91

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Question 92

A team member does not understand what the project risks are or the impact that they could have. How should an agile leader communicate risks in a way that the team will understand?

Options:

A.

Create a RAG chart (responsible, accountable, consulted, informed) that identifies who is accountable for each risk.

B.

Create a Gantt chart that includes slack to accommodate for unknowns.

C.

Create a communications management plan that details who is responsible for communicating risks.

D.

Create a risk burndown chart showing the reduction of risks overtime.

Question 93

Following an upgrade, a software support team is overwhelmed by the number of tickets being submitted by end users. The team's manager is pushing the team to "work smart" by focusing on activities that deliver the most value in the least amount of time.

What should the team do?

Options:

A.

Work longer hours to complete more of the support backlog.

B.

Work support tickets in the order in which they were received.

C.

Place tickets on hold until the team completes an analysis of the backlog to identify and resolve systemic issues.

D.

Add members to the support team.

Question 94

During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Question 95

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

Options:

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Question 96

During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Question 97

An organization is undergoing an agile transformation to improve its market position. Management wants minimal overhead in connection with the agile initiative and wants the agile teams to control the work in process (WIP) and ensure that iterations do not result in waste.

Which approach should be used in this scenario?

Options:

A.

Feature-driven development

B.

Extreme Programming (XP)

C.

Scrum

D.

Kanban

Question 98

What should a team do when they complete all sprint goals earlier than expected?

Options:

A.

Begin working on an item in the backlog

B.

Ask the scrum master to select an item from the backlog on which to work

C.

Ask the product owner to select an item from the backlog on which to work

D.

Jointly decide with the scrum master on an item from the backlog on which to work

Question 99

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options:

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Question 100

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint goals What should the scrum master do next?

Options:

A.

Alert the team that sprint goals might not be met and create an alternative plan

B.

Obtain team buy-in to perform modifications to the sprint backlog.

C.

Have the sprint proceed as planned

D.

Ask the team to decide if the task should be reassigned

Question 101

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

Options:

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Question 102

A scrum master wants to encourage better collaboration within a collocated team and is coming up with a visualization method for the project. How could the scrum master promote transparency?

Options:

A.

Consolidate the team's updates in presentation slides and email them to the team regularly.

B.

Radiate key information such as the team's work, progress, and velocity at the team's common area.

C.

Share team progress individually with each top performer every week.

D.

Attach sticky notes for each assignment to the wall in the team's area.

Question 103

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing it's teams.

What strategy should be employed to re-organize the teams?

Options:

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption andcapitalize on synergies

C.

After grouping individuals by role multi-discipline teams should be created that are comprised of one member from eachrole

D.

Features should be prioritized and then teams should be organized around those priorities

Question 104

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Question 105

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

Options:

A.

Reduced or improper customer collaboration.

B.

Reduced or improper product knowledge by the development team.

C.

Reduced or improper release planning.

D.

Reduced or improper product specification.

Question 106

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?

Options:

A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.

B.

Collect updates from each team member before the meeting and share them with all members.

C.

Ask the team member to update daily progress on the information radiators.

D.

Change the team velocity to show positive progress in shared information radiators.

Question 107

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

Options:

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.

B.

Ask the product owner to review their items with the product owner's teammates before adding user stories to the backlog.

C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.

D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.

Question 108

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

"Inspect and adapt" are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member's opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for thesprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Question 109

For what is the MoSCoW method used?

Options:

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Question 110

Throughout the project, an agile practitioner notices that one team member is becoming an emergent leader. What should an agile practitioner do?

Options:

A.

Present opportunities in order to be supportive and grow that team member's talents.

B.

Encourage the team member to fit in more with the established team norms.

C.

Bring this to management's attention so they don't disrupt the team.

D.

Ask team member to respect defined roles on the project to avoid confusion with the team.

Question 111

A project sponsor is upset that an enhancement will be unavailable until next year. What should the product owner do?

Options:

A.

Accept responsibility for the product's delay.

B.

Ensure that the project sponsor's priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Question 112

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Question 113

A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.

How should the project manager proceed?

Options:

A.

Consult with the product owner to prioritize the new work at a higher level.

B.

Consult with the project sponsor and project team to resolve the issue.

C.

Consult with the project team to rework the existing estimates.

D.

Consult with the product owner and project team.

Question 114

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Question 115

The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.

How should an agile team member coach the VP and teams be more effective?

Options:

A.

Coach the chief information officer (CIO) on implementation of agile benefits and expectations.

B.

Coach the teams on implementation of agile benefits and expectations.

C.

Coach the managers on implementation of agile benefits and expectations.

D.

ICoach the vice president (VP) on implementation of agile benefits and expectations.

Question 116

An agile team has received several new features to be added to the product backlog. The team is struggling to provide a reasonable estimate for feature development due to a lack of experience.

How should an experienced agile practitioner assist the team?

Options:

A.

Add a task to the product backlog to allow the team time to investigate and experiment prior to estimating.

B.

Add a task to the product backlog to allow the team to apply a wideband Delphi estimation technique.

C.

Add a task to the product backlog to allow the team to apply planning poker to estimate the effort.

D.

Add a task to the product backlog to allow the team to apply a three-point estimation technique.

Question 117

What should an agile practitioner do to ensure that the end product meets business requirements?

Options:

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders.

D.

Confirm managers and stakeholders are invited to product review meetings

Question 118

An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap?

Options:

A.

Product vision, business objectives, themes, timeframes, and disclaimers

B.

Product improvements, resource management, risk management, and deadlines

C.

Product goals, strategic objectives, major features, and release plans

D.

Features, stages of development, technology and infrastructure, dependencies, and risks

Question 119

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Question 120

A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team's servant leader do?

Options:

A.

Try to motivate the team by recounting examples of their past successes.

B.

Ask the team to find user stories from similar projects for this customer.

C.

Ask the team to restate the requirements and review them with the client.

D.

Ask the team to develop user stories and build deliverables based on the requirements.

Question 121

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, the junior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, thejunior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

Options:

A.

Escalate the issue to the functional manager and request another team member with more experience.

B.

Ask the team to refer to the team charter on how to resolve this kind of impediment and help the team member.

C.

Coach the team by reminding them that a self-managed team requires everyone to be able to remove their impediments.

D.

Remind them that self-managed teams require everyone to be honest and supportive of one another to resolve impediments.

Question 122

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

Options:

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Question 123

At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity. How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Question 124

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.

What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Question 125

A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the firstmeeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.

What should the project manager do next?

Options:

A.

Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.

B.

Identity and create personas that can help the team better understand the needs of the target user base.

C.

Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).

D.

'Engage the human resources (HR) team to identify the key users and interview all of them accordingly.

Question 126

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

Options:

A.

Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.

B.

Create a spike story to determine what needs to be done to use the new interface.

C.

Lower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings.

D.

Move the work to the vendor, since they have better knowledge of interface implementation.

Question 127

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Question 128

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

Options:

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Question 129

A team member has asked a question about the responsibilities of the product manager, QA, and the team regarding quality. What should the agile project manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member's role may vary as stated in the definition of done (Do

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the product manager defines the functionality from end to end.

Question 130

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Question 131

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

Options:

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Question 132

During a sprint review the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint What should the product owner do next?

Options:

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Question 133

During team meetings, the team often struggles with making decisions about their technical approach. What should be done to improve the quality and timeliness of decisions?

Options:

A.

Work with the team to improve collaboration by fostering group decision making and conflict resolution techniques.

B.

Promote team discussion but give the product owner the ultimate decision making authority.

C.

Assign individual team members as decision owners for each key decision to avoid conflict.

D.

Identify team members that demonstrate servant leadership qualities to facilitate discussion and make decisions.

Question 134

An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" - a story-telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.

What is the project leader trying to create?

Options:

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other's weaknesses and strengths.

Question 135

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Question 136

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Question 137

A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.

What should the agile facilitator do?

Options:

A.

Dismiss the rest of the team from the meeting to focus on the problem reported by the team member

B.

Ask the team member to wait to discuss until the next daily coordination meeting, the team needs to review the current status.

C.

Inform the team that the meeting will be extended so there is time to hear what the team member is reporting

D.

Stop the team politely and suggest scheduling another meeting to discuss this specific matter.

Question 138

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

Options:

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Question 139

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

How many sprints will be needed to complete the entire backlog?

Options:

A.

15

B.

16

C.

17

D.

18

Question 140

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

Options:

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Question 141

A mature agile team welcomes a new member Due to poor experiences with a previous team, the new member is reluctant to communicate.

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Question 142

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Question 143

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used.

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function.

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Question 144

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Options:

A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.

B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.

C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.

D.

Implement a spike lo enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working

Page: 1 / 48
Total 482 questions