Which one of the following comes first in the project plan?
You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory
__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.
Which of the following is an output of Verify Scope?
The main purpose of project initiation is to ________.
The main purpose of project initiation is to ________.
Which monitoring or controlling activities would not result in preventive action being applied?
Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.
Administrative Closure should occur ___________.
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
You are the project manager of a project that just went into extinction mode. This means that your project __________.
A contract cannot contain _____________.
_________ is always the lowest risk for the buyer if the scope of work is not well defined.
If a project with a SPI of 1.8, what you tell?
Which of the following is conflict resolution technique?
ISO Stands for __________.
Create Procurement document is done in _______.
Which document formally authorizes a project?
If a project with a CPI of 1.2, what you tell?
Project success can be achieved only if:
You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?
What are the inputs for Initiation process?
Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.
When you are developing the estimates for project, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation method are you using?
During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.
Acceptance of the product should be ________.
A Project Management Office (PMO) manages a number of aspects, including what?
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Which contract type is typically used whenever the seller's performance period spans a considerable period of years?
What is the first step in preparing the risk register?
The Monitoring and Controlling process group contains which of the following processes?
Company A bought a well-defined project deliverable from Company B. Company A will pay a fixed total price plus a percentage premium for the schedule target achieved.
For which type of contract have they subscribed?
What risk technique is used to quantify the probability and impact of risks on project objectives?
Which of the following is an input to the Qualitative Risk Analysis process?
When managing a project team, what helps to reduce the amount of conflict?
What is a technique used in the performance reporting process?
A project manager needs the project team to make a group decision. Which of the following is a method that can be used to reach a group decision?
Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
Which of the following equations is used to calculate cost variance?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
CO = $7,000
CM = $10,500
CP = $11,000
What is a cost of nonconformance?
Which of the following is an output of Define Scope?
The degree of risk shared between the buyer and seller is determined by the:
How many knowledge areas are there according to PMBOK Guide?
In which tool and technique is it possible to find a correlation between dependent and independent variables?
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
The project management information system is used as tools and techniques in which of the following processes?
In which of the following team development stages does the team begin to work together, develop trust, and adjust to the work habits and behavior?
Which of the following is a project constraint?
If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?
An input required to develop a preliminary project scope statement is:
Which of the following is NOT an input of Estimate Costs?
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?
A process that is not part of a Project Risk Management is:
If a project with a CPI of 1.6, what you tell?
Which is the most risky phase of a project?
You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is ___________.
You are the project manager and you have created a contract for your customer. The contract must have ________.
Purchasing insurance is an example of __________.
What are common types of cost-reimbursable contracts?
Which of the following is NOT an example of a type of schedule report?
You are the project manager of a project. Your project just went into integration mode. This means that your project __________.
In which type of organization, a project manager is in complete control of the project?
Customer formally accepts the deliverables of each project phase. This process is known as ________.
Which document formally authorizes a project?
What is the purpose of the WBS?
Which is not included in Performance improvements :
The activity that is most concerned with the current status of the project schedule is called ___________.
What are the outputs of Initiation process?
A Project Scope Management includes :
Which of the following is ensuring that all features and functions are included in a product or service
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
When should a project manager be assigned to a project?
In which phase you define the final deliverable?
In which type of organization, a project manager is in complete control of the project?
A Project Cost Management plan is created as a part of: