Which of the following is a Governance document?
Which of following is correct about Benefits Management?
The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.
Is this an appropriate application of the 'structure' theme, and why?
The CFO has been appointed as the SRO for the Smart Meter Programme.
Is this appointment an appropriate application of the ‘organization’ theme, and why?
Which of the following statements is FALSE?
Which of the following statements best defines 'MSP Principles'?
Which of the following is NOT an MSP Governance Theme?
Which of following is a key attribute for a SRO?
At which transformational flow basic programme controls are established?
The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?
Here are three statements about the programme justification for the Smart Meter Programme. In which document should the statements be recorded?

In delivering the capability, which role is responsible for aligning projects with programme objectives?
In Managing the Tranches, which role is responsible for preparing for the next tranche?
Which of the following is Not one of MSP defined levels of stakeholder engagement?
Which of the following is Management document?
Who produces Business Case?
Where in the transformational flow would the Benefits Map normally be created?
In delivering the capability, who is responsible for aligning projects with benefits realization?
Which of following is NOT part of delivering the capability?
Which of the following is NOT normally a characteristic of the Vision Statement?
Which document is created from Programme mandate and works as input for Business Case?
The CFO has specified the need to calculate the Net Present Value (NPV) to demonstrate the return on investment for the programme. How should the resulting benefit be expressed?
Select the best option defined by following sentence: 'Action of carrying out the coordinated organization, direction and implementation of dossier of projects and transformation activities to achieve desired outcomes'
For a business transformation programme, which of scenarios will lead to high probability of success?
At the start of the programme, the programme manager listed some design-related actions to be completed. Which role is MOST focused on each task?

Which of following is output of 'Defining the programme'?
Which of the below is not a critical organizational element?
The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.
Which role should be responsible for managing these activities?
The CFO has informed the programme board that the predicted increase in electricity and gas customer numbers is too optimistic. The BCM has produced new targets based on this new information. The programme manager has updated the target operating model to reflect this.
Is this an appropriate application of the ‘align with priorities' principle, and why?
Which of below sentences best defines programme management?
During the ‘plan progressive delivery’ process, it was decided that the call centre managers would hold a weekly meeting with all call centre staff to update them on progress and understand any concerns that they might have. This information was documented by the programme manager.
Which theme is being applied?
The programme is in the 'identify the programme' process. The CEngO is concerned that the engineering department will not be able to deliver the proposed Engineering Department Work at the same time as supporting the research into new smart meters and water leak detection equipment. The programme board believes that the engineering department will be able to manage, if the programme is planned optimally.
Which role is MOST LIKELY to approve the programme board's recommendation?
Which of the following is not true about programme control?
Which of the following will not be in Issue register?
The task of organizational realignment relies heavily on getting results from existing staff and enhancing skills. Here are items of information to be recorded in the stakeholder engagement and communications plan. Under which heading should they be recorded?

The programme is in the ‘embed the outcomes’ process at the end of Tranche 2. As part of the adopt the capabilities activity, the BCM is concerned that many of the sales staff are continuing to use the old sales system alongside the new systems and processes. This is impacting on cost reductions and increased sales. The BCM has confirmed that the new system has all the functionality required.
As part of the ‘adopt the capabilities' activity what should the BCM do to resolve this situation?
Which of the following statements best defines 'transformational Flow'?
Which of below sentences describes Project Brief?
UU has always used a linear project management methodology in the past with varying degrees of success. During the ‘design the outcomes’ process, UU has decided to trial an agile approach to deliver projects throughout Tranche 1.
Which theme is being applied to the ‘design the outcomes' process?