Failure probability of mechanical equipment components is high, and management wants to keep downtime to an absolute minimum.
Which is the best spare part option to choose?
The needs analysis has been completed and the data center organization is tasked with the capability assessment.
Which of the below is a mandatory activity as part of the capability assessment?
The organization is preparing for business continuity.
Due to the current economic situation, management wants to spend as little money as possible on an alternative facility.
Which option should you propose?
In what situation can an individual applying for a security job be exempted from a background screening?
The data center service provider has decided that maintenance of the data center facilities infrastructure will be outsourced.
Is it still involved in the risk management process of data center maintenance?
According to the World Economic Forum, which of the below is the largest global risk of the next decade?
Data center operators complain about receiving too many non-alarm conditions.
What is the best response?
To set up a framework for an effective environmental management system, which standard should be followed?
Which process is not part of the 6-step document management life cycle?
What is the outcome of a risk evaluation process?
What describes the term predictive maintenance?
During lock-out/tag-out, which of the below is the most recommended procedure?
The organization is implementing an information security management system (ISMS).
What is the common process model to follow?
What is equipment life cycle management?
During what project phase do you need to start involving the stakeholders?
Several data center services in the service catalog charge the customer on the actual usage of those services.
What chargeback model is applied?
Heavy equipment needs to be moved to another side of the computer room so that the three (3) workers can continue their drilling and cutting off the wall for a new cable tray. Four (4) staff members are required to move the equipment so there is one extra staff member required to assist. The safety manager who is overseeing the works is asked to help moving the equipment.
Is the safety manager allowed to step in and assist with the move?
When creating a compliance document register, which categories should at least be included?