Big Black Friday Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70special

Construction Specifications Institute CDT Construction Documents Technologist Exam Practice Test

Page: 1 / 12
Total 120 questions

Construction Documents Technologist Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$37.5  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$33  $109.99
Question 1

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Question 2

The architect/engineer reviews submittals for which of the following reasons?

Options:

A.

To correct or change the design

B.

To monitor design conformance

C.

To review installation procedures

D.

To review substitution requests

Question 3

Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?

Options:

A.

Architect, supplier, and contractor

B.

Owner, stakeholders, and participants

C.

Public, private, and environmental health

D.

Owner team, contractor team, and design team

Question 4

When is decommissioning required for a facility?

Options:

A.

When the entire building is going to be demolished

B.

When the facility is no longer needed for operations

C.

When the facility will not be used again in the future

D.

When the building changes owners

Question 5

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Question 6

What could a reference standard specification be based upon?

Options:

A.

Project manual for similar project

B.

Design intent

C.

Trade association standard

D.

Manufacturer's specification section

Question 7

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

Options:

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Question 8

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Question 9

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

Options:

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Question 10

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

Options:

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.

Question 11

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

Options:

A.

Workflow meeting

B.

Preinstallation meeting

C.

Progress meeting

D.

Schedule monitoring meeting

Question 12

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?

Options:

A.

Methods technique

B.

Critical path method

C.

Front end loading

D.

Schedule of values

Question 13

How do private bidding practices compare or contrast with public bidding practices?

Options:

A.

A private owner may waive any informality in the bidding, except for the performance bond.

B.

Private bids may be opened in private, but the results must be published in a reasonable time.

C.

The laws and regulations for private bidding are the same as for public bidding.

D.

The private owner may award a contract to a responsive and responsible bidder other than the lowest.

Question 14

Which of the following is a component of the contract documents?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Question 15

Who is responsible for accepting and inspecting for damage of the owner-furnished products delivered to the project site?

Options:

A.

Contractor

B.

Installer

C.

Owner

D.

Subcontractor

Question 16

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Question 17

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Question 18

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Question 19

What does Divisions 02-49 of the construction project manual address?

Options:

A.

Procurement instructions

B.

Distinct work results areas

C.

Temporary facilities and controls

D.

Life cycle activities

Question 20

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:

A.

The construction schedule

B.

The subcontractor’s invoices

C.

The schedule of values

D.

The percentage of completion

Question 21

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Question 22

An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?

Options:

A.

The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.

B.

The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.

C.

The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.

D.

The electrical engineer does not need to control how the work is to be assigned to subcontractors.

Question 23

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Question 24

Which of the following ensure that all systems work together effectively to meet the overall project performance goals?

Options:

A.

Total project commissioning

B.

Inspection by architect

C.

Safety testing

D.

Field testing

Question 25

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Question 26

Where can you typically find requirements for temporary toilet facilities?

Options:

A.

Supplementary Conditions

B.

Division 22 – Plumbing

C.

The Owner–Contractor Agreement

D.

Division 01 – General Requirements

Question 27

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Question 28

Which documents are commonly included as procurement documents?

Options:

A.

Project record documents

B.

Contract documents

C.

Consensus documents

D.

Bidding documents

Question 29

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

Options:

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Question 30

Who is responsible for planning, maintaining, and supervising construction safety measures and programs?

Options:

A.

Architect/engineer

B.

OSHA

C.

Owner's inspector

D.

Contractor

Question 31

Who has the right to stop the work if hazardous materials are encountered during the construction?

Options:

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Question 32

Which is the reference document that includes guidelines and tools for the organization and presentation of design and construction drawings?

Options:

A.

AIA CAD Layer Guidelines

B.

National Institute of Building Sciences

C.

National BIM Standard – United States

D.

U.S. National CAD Standard

Question 33

Which of the following should be avoided when specifying warranties?

Options:

A.

Requiring or permitting a warranty that strengthens the owner's rights

B.

Requiring minimum warranty coverage available for a particular product

C.

Including language to require warranties extending beyond the contractor's one-year correction period

D.

Relying on a warranty as a substitute for thorough investigation of a product and its manufacturer

Question 34

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Question 35

Why should project closeout meetings be held?

Options:

A.

To set substantial completion

B.

To resolve subcontractor disputes

C.

To commission the project for occupancy

D.

To review handover procedures and activities

Question 36

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Page: 1 / 12
Total 120 questions