Given the following network diagram:
Which of the following is the critical path?
A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Which of the following is a quality assurance tool?
A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?
Which of the following is the most important activity for the project manager during the closure of a project?
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?
Which of the following aspects are true of waterfall as compared to agile? (Select two).
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
Which of the following are primary features provided by a standard laaS solution? (Select two).
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?
Which of the following statements best represents a network issue?
Which of the following contract types in project procurement has the highest risk for the buyer?
When assigning access, classifying information based on sensitivity is referred to as:
A project team member wrote a user guide over the past ten days. Given the following scatter diagram.
Which erf the following can be formally conducted?
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
A team member identifies a critical issue in production. Which of the following should the project manager apply?
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the
following has the project manager identified?
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
Which of the following statements best describes Kanban?
A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?
A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)
A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
Which of the following is an intended outcome of a stand-up meeting?
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
Which of the following can be used to determine whether a sample product is within an acceptable range?
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
How does data discovery assist with data classification'?
During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?
A)
B)
C)
D)
As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
Which of the to and allowing interactive feedback from a project team?
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
Which of the following activities should a project manager perform during the closing phase? (Select three).
During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:
Which of the following issues should be addressed FIRST?
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
Which of the following requires the MOST availability from the business team?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?
A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
• Two developers
• High uncertainty about existing systems
• Risk of frequent requirement changes
• Tight deadlines
Which of the following project methodologies would be best to use in this situation?
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?
A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:
Which of the following most likely represents the number of items in the backlog?
An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?
Which of the following activities are performed during the closing phase? (Select three).
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
Which of the following should be considered first when determining the privacy management for project data?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?
One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?