Which of the following would require that the project risk register be updated?
A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?
A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:
Which of the following are examples of a good business case for a new project? (Select Two).
A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?
The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:
A project manager wants to have complete control of the project team members. Which of the following organization structures would allow for this?
The communication plan for a project is a subset of which of the following documents?
Two SMEs disagree with the designed plan for a particular component. The project will be delayed if the plan is not approved today. The project manager demands the SMEs work together to incorporate their modifications by the close of business today. Which of the following resolution techniques was used?
A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?
Which of the following should a project manger do to actively track issues as they are identified?
A project has been cancelled during the execution phase. Which of the following steps should be taken?
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
Which of the following is the primary purpose of a project tollgate?
All of the following are taken into account when determining the critical path EXCEPT:
After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?
Refer to the attached Exhibit.
Which of the following is the float of path Start-C-E-Finish in the network diagram?
Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).
Project information is received by the project manager in a number of different formats from team members. Which of the following would be the BEST way for the project manager to standardize the information?
Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?
A cause and effect diagram can also be called:
All of the following are considered part of the risk management plan EXCEPT the risk:
Which of the following is a benefit of the work breakdown structure (WBS)?
Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?
A project can be defined as which of the following?
Which of the following elements would be needed to prepare an effective project scope document?
Which of the following is created using the work breakdown structure (WBS) as an input?
Which of the following should be created in the project closing documentation? (Select Two).
In which of the following organization types would a project manager have the MOST authority?
Which of the following shows a project that is presently over its financial budget?
Which of the following activities are associated with a project kick-off meeting? (Select Two).
A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?
The greatest amount of conflict occurs in which of the following team development stages?
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
Which of the following sequences represents the correct order for implementing a change request?
A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
The project manager has outsourced a call center to a company in another region. The project manager receives reports that customers sometimes cannot hear the instructions given by call center employees. Which of the following is the MOST likely cause of the reports?
In regards to proper change management procedures, which of the following would be the FINAL activity?
Which of the following is the FINAL step in pre-project setup?
An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:
A project manager has noted that a vendor is providing a poor quality product. The vendor states that its products meet the quality standards outlined in the current contract. Which of the following documents outline the contractual requirements?
Which of the following would be the MOST important objective of a kick-off meeting? (Select Two).
A project manager receives a request for a minor change to one of the deliverables. Which of the following documents would MOST likely be impacted?
The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?
Three of the team members are having a conflict with each other. Which of the following steps should the project manager take to minimize the conflict?
Which of the following would be considered a valid strategy in response to an adverse risk?
To ensure the quality of implemented project change requests, which of the following will need to occur? (Select Two).
Which of the following is included within the RFP?
Which of the following is a characteristic of a project charter?
A manager and the head of engineering discuss a change to a major work package. After the meeting, the project manager contacts a third person and tells them to complete the paperwork to make the change. Who did the project manager contact?
Which of the following would a project manager do NEXT after selecting a vendor for a project?
Pareto charts helps the project manager with which of the following?
During handover stage a customer of a particular project noticed the extended warranty from a particular vendor for a critical application has not been ordered. In which of the following documents should this have been previously addressed?
Which of the following documents is used when assigning resources to scheduled tasks?
The project manager has the MOST authority in which of the following organizational structures?
Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
A project manager has an initial problem with a remote team members performance. Which of the following is the BEST form of communication to address this issue?
Which of the following are reasons why formal project closure is important? (Select Three).
Who has the MOST control over project scope changes?
When are project closure procedures determined?