A state-owned company engaged in a change project faced a major issue related to its image as a socially responsible organization. What could the leaders do to ensure the outcomes remain consistent with the company vision?
In which stage of the project timeline should integration of change management and project management plans be considered?
The change management strategy was completed and implemented on time; however, while the technical aspect of the change appears to be successfully undertaken, a large number of stakeholders appear not to be able to adopt the change. Which strategy is best revisited to address this situation?
During a program-planning meeting, a team participant suggests that all communications to the business be contained within a standard weekly email delivered at the same time using a standardized format. What reasons could the change lead use for ignoring this suggestion?
What is the primary purpose of conducting a learning needs assessment?
What approach would you take to ensure an individual’s engagement on a change effort?
What process identifies those affected by the change and those with the ability to influence the outcome?
When conducting a change risk assessment, which key source inputs should you take into consideration when identifying potential risks?
Who should be involved to ensure the credibility of measuring change achievements?
What should a learning and development strategy be able to demonstrate?
After communication meetings with all employees impacted by a change initiative, the feedback was that many of them do not understand the reasons for this change. Which part of the communications strategy is most likely to be revised to achieve desired outcome of change communication?
Which task in change management defines the approach, scope, roles and responsibilities in undertaking detailed impact analysis and readiness planning for implementing the change?
There are numerous activities that are part of executing the sustainability plan. What is the risk if they are not effective?
As the change lead for a new sanitation project in Nigeria, you are defining success criteria as well as measures to monitor if the implemented change is achieving its expected benefits. What are you developing?
What are three key inputs for developing a sponsorship plan?
What document should provide guidance and best practices for future change initiatives?
What is an example of a tangible indicator that is used to evaluate the effects of learning?
The first two weeks of a large and complex change project is underway and things seem to be going okay. What have you developed so that you can be sure the change is on track?
What is a primary purpose of conducting the lessons learned evaluation?
What is the most effective approach to avoid duplication of efforts and increase stakeholder awareness regarding change management and project plans?
The vice president of marketing is the sponsor for a major change initiative. She recently accepted a new assignment in the international customer care organization and is leaving the vice president of marketing position. No replacement has been named. What is the potential project impact caused by losing a sponsor?
The change project is ongoing but the sponsor is concerned about the readiness of the business and has asked for a change manager to be brought in. The project manager has never before worked with a change manager. What is an appropriate first measure for the change manager to take?
The change lead is reviewing the market factors, capacity and saturation, which address key characteristics and attributes of the organization and the proposed change. What type of activity is the change lead most likely conducting?
You are in the role of identifying obstacles to achieve the desired future state. What document are you likely to have as an output of this effort?
How would a change manager ensure that managers and supervisors are equipped with the tools they need to assist their employees through a change process?
Which characteristic is likely to bring more disruption in an organization-wide change initiative?
A credit card organization currently has multiple related change initiatives. The second initiative is taking longer than expected due to delayed access to subject matter expertise in a particular area. Which portion of the change management plan for the delayed initiative is directly impacted by this subject matter expertise requirement?
What is a key objective of completing a change management effort?
What document does a change management team develop to ensure senior executives are actively involved and visibly participating throughout the change initiative?
In resource planning, after defining key roles for each type of labor needed to support the change effort, what is the next step to determine if the skills required exist in the organization?
What refers to the extent to which an organization uses change management and project management methodologies, techniques, and tools?
What are three main components you should include in a communications plan?
An ongoing change program is gaining momentum and throughout the organization stakeholders face challenges and experience success. What needs to be clearly defined in the communications plan to support them?
Why is a sponsor important in a change effort?
What is the key factor to consider when assessing the organizational readiness for a change?
For a small restaurant that recently doubled in size, what factor would be the most likely to limit the organizational capacity for a change to a new IT system?
You are currently leading a major ongoing change initiative. You observe that the project lacks support, lacks active engagement in the change effort and loses interest in the change effort. Under the circumstances, what would be the best strategy to address this constraint and enable an intervention to happen?
What is the most significant element to look for when conducting an assessment of an organization's capacity for change?
A change in leadership resulted in a need to adjust an existing change management plan. To maintain momentum, what needs to happen after these adjustments are approved?
You have been hired to manage an ongoing transformation initiative in an organization. You immediately observe that leadership is noticeably absent in that most of the leaders are unclear about their role. What plan would you develop to address this gap?
How can you improve your communications plan to ensure the right messages will be delivered at the right time?
What could be a significant input to the analysis of change objectives and in defining next steps?
What element included in a stakeholder engagement plan ensures that the plan meets the intended outcomes?
What is a key consideration when developing a change management plan?
The change project aims at growing market shares for division X. Over the past weeks customers have been indicating that they are not ready for the new product line. What do you need to do to decrease the speed of change?