Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
Why does activity 11001 not show successor activities?
You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?
Determine the correct formula and date for the late finish for Activity 2001.
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?
Which of the following is NOT required when initially planning a project?
During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?
Estimate to complete (ETC) is __________________.
When should the Project Plan have incorporated the relevant interfaces and requirements of the project contract documents?
If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?
Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Budgeted cost of work scheduled is _______________________.
The Cost Estimate is NOT developed to:
The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:
What is the remaining work duration of Active D?
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
Which of the following is the most important scheduling consideration for the BILCO contractual scope?
The work breakdown structure is used to organize
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor has included several reports with its submittal, including a report that sorts all activities by total float. What is the value of this report?
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
What problems can a soils engineer deal with on a project?
The best source of project risk or opportunities is:
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?
In its simplest form, what is the main drawback of critical path method scheduling?
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
Which of the following will always describe the critical path? The path with
How could the structural steel drawing delay have been prevented?
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?
Which of the following is NOT required when performing weekly or monthly schedule updates?
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
What is a critical path method schedule?
Prior to the start of work, Management determined the need to make the Product available 10 workdays earlier than planned. Which activities need to be expedited?
At a minimum, periodic reporting must be done at what interval?
Determine the driving activity for Activity 10001.
What project cost elements would NOT normally be reflected in the Activity 1000?
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:
Resource planning must take all of the following into account except for:
At the end of month one, did the delay to the parking structure foundation delay the project?
If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
Should activities be coded with the EBS value?
Which statement is true?
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
These are the activities on the critical path:
Which activity is drawn in the incorrect position?
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
What is the relationship depicted between Activity G and Activity H?
The project goals_________.
Determine the correct formula and date for the late finish for Activity 6002.
As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?
Which of the following is NOT input data to the construction planning process?
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using